Conventional precision metal manufacturing time cycle, weeks or even months, competitive market under the conventional production is difficult to meet the market demand and product replacement, and how to adapt to market demand to shorten the production cycle?

We believe that the key to investment casting is to make full use of its flexible functions and incorporate as much value as possible into the casting, because we will provide you with a better investment casting production plan.

• For the launch of new products, we provide more precise delivery time, high-quality prenatal preparation to meet your product release time.

• We provide lean production planning and capacity analysis for small, medium and large volume operations according to your product schedule, achieving true no-stock, on-time delivery.

• Innovation standards-Our experts are not imitating, but in constant innovation.

• Our in-house operations will provide you with a full range of project services, including machining, heat treatment, final finishing.

Additional services include the production of molds, various fixtures, and 3D printing.

 

Different types of production lines, fast delivery time, fast delivery of various products, fast line change, fast delivery.

 

Process

Regular time

benchmarking time

Mold

3-4 weeks

2-3 weeks

Sample

6-8 weeks

4-6 weeks

Customer Review

1-2 weeks

1-2 weeks

First batch

6-8 weeks

3-6 weeks

Overall

16-22 weeks

10-17 weeks

 

Reorder Production Lead Time

Most investment casting companies take a few days, while we have reduced the production cycle to a few hours.

 

Process

Regular time

benchmarking time

Scheduling

20-45 days

1-7 days

Wax type

4-7 days

8 hours

Shell Making

7-14 days

2-6 days

Dewaxing

7-14 days

4 hours

Casting

3-5 days

16 hours

Cleaning

3-7 days

8 hours

Heat treatment

5-10 days

16 hours

Finished products

4-5 days

24 hours

Transportation

1-2 days

24 hours

Overall

8-16 weeks

7-14 weeks

 